The volume formula for boards and beams

A board or a beam is a rectangular block, so the same formula covers both: volume equals length times width times thickness. For a batch of identical pieces, multiply the result by quantity.

Metric: V = length × width × thickness × quantity, with all three dimensions converted to meters (divide millimeters by 1000, centimeters by 100) to get cubic meters (m³).

Imperial (board feet): the North American lumber trade prices volume in board feet, not raw cubic feet. Board feet = (thickness in inches × width in inches × length in feet) ÷ 12. One board foot equals 1" × 12" × 1ft, or 0.00235974 m³.

Metric example: a board

A board 6000 × 150 × 25 mm, quantity 20. Converted to meters: 6 m × 0.15 m × 0.025 m.

Volume per board: 6 × 0.15 × 0.025 = 0.0225 m³. Batch volume: 0.0225 × 20 = 0.45 m³.

Board-feet example

A board roughly 1" thick × 6" wide × 12ft long, quantity 20 — close to the metric example above (25 mm ≈ 1", 150 mm ≈ 6"). Board feet per piece: (1 × 6 × 12) ÷ 12 = 6 board feet. Batch: 6 × 20 = 120 board feet.

Cutting waste

Real cuts lose material to sawdust and offcuts, so a waste margin is usually added on top of the raw volume — commonly 10%, though the exact figure depends on the cut type, blade kerf, and number of cuts. With waste: final volume = V × (1 + waste% / 100).

For the board example above, a 10% waste margin turns 0.45 m³ into 0.495 m³ (≈132 board feet instead of 120) for the same 20-piece batch.

Manual calculation vs. a calculator

For one or two pieces, doing the math by hand is fine. Once a cut list reaches 20–30 lines across different sections and materials, it becomes easy to mix up a unit conversion or forget to apply waste to one row — the kind of small mistake that throws off an actual material order.

SawYield’s cut list runs this same formula across your whole list at once, switches between metric and board-feet pricing per material, applies the waste margin automatically, and recalculates the moment any dimension or quantity changes.

Once you know the volume, the next practical question is usually cost. See How Much Does a Cubic Meter of Edged Lumber Cost for what actually drives the price.

Calculate your own sizes← All articles